On behalf of Netze BW, we connected eleven buildings to the existing gas network.
A new gas pipeline was laid in a 600 m long trench to enable eleven more houses to be supplied with gas. This involved laying both asphalt and paving stones.
In addition, we were also able to co-lay a pipeline on behalf of the Enzkreis special-purpose association. This involved the laying of 305 m of pipe bracing. The planning and surveying was carried out by our company.